WEEKLY TRACKING
Construction
and installation status
guestrooms with completed inspection
STATUS BY ACTIVITY
Consolidated view
OVERALL STATUS BY FLOOR
Space distribution
Select a floor to view progress by activity.
204 SPACES
General tracking
| Space | Commercial no. | Type | Floor | Status | Last updated |
|---|
GUESTROOM READINESS & INSPECTIONS
Handover status
“Ready for inspection” is Ecoarea’s declaration. “Inspected” means Engexpor issued a snagging report. Neither status means that corrections are complete or that the guestroom has been accepted.
ECOAREA
Ready for inspection
60 rooms reported by Ecoarea. Room 240 was explicitly excluded from Stéphane’s list.
ENGEXPOR
Inspected
38 rooms with a completed report. Rooms 113 and 119 were obstructed and are not counted as inspected.
CONSTRUCTION SCHEDULE
Summary schedule
EXECUTION NOTES
2nd Floor — construction may extend in some areas; room 201 is excluded.
1st Floor — rooms 104 and 105 may be affected by the Meeting Room; room 138 may be constrained by IT storage.
3rd Floor — zone D depends on completion of the wardrobes.
GENERAL NOTES
Guestroom entrance doors are being reworked to include closers. Architectural lighting is included in Construction; decorative lighting is included in FF&E. ADD niches and subwoofer integration remain under confirmation.
ACTION & RESPONSIBILITY TRACKER
Pendencies
| Issue | Owner | Priority | Status | Due | Latest update |
|---|
SHARED DOCUMENTATION
Projects
THE STANDARD LISBON
Project library
Open a discipline to view or download its files. Documents are shared in view-only mode.
CONSTRUCTION
Construction
INTERIOR DESIGN
Interior design
CONSULTANTS
Consultants
PURCHASING PROCESS
Purchasing process
To download from Google Drive, select a file or folder and choose Download.